Samara Arena Way Off Schedule


Recommended Posts

Quote

FIFA says the World Cup stadium in the Russian city of Samara requires "a huge amount of work" to be ready on time.

With less than three months remaining before the 45,000-seat venue is due to host a Group A match between Costa Rica and Serbia, the pitch has yet to be laid.

Construction work at the Samara Arena, one of 12 venues that will stage World Cup matches this year, has been hit by a number of setbacks in recent months, putting authorities under additional pressure to deliver a proper venue for the tournament.

Link to comment
Share on other sites

Sign up to remove this ad.
  • Replies 1
  • Created
  • Last Reply
  • Administrator

still doesn't have a pitch laid on and cold weather preventing this.

Quote

 

With less than three months to go until the World Cup, the 45,000-seat Samara Arena is the only one of 12 stadiums which doesn’t yet have a pitch installed.

The stadium in the Volga River city of Samara was already badly delayed due to a complex roof design, but now cold weather in the Russian spring is causing further problems. The pitch can’t be installed until the weather warms up.

“Obviously we would expect further progress than this,” FIFA’s chief competitions official Colin Smith said on a visit to the arena Wednesday. “We don’t yet have a pitch, and obviously we need to wait for some warmer weather conditions in order to get this pitch installed.”

As of Tuesday, instead of a field, there was an area covered with tarpaulins and snow. Temperatures are forecast to stay slightly below freezing for the rest of the week.

“There’s a huge amount of work still to be done,” Smith added. “From the information we’ve received there’s nothing stopping all these areas being completed on time. It just requires commitment and more manpower to get it done on time, and when we talk about on time, we’re talking about the commissioning date of the end of April.”

If that date passes, it could restrict FIFA’s ability to test the stadium with Russian league games and install World Cup equipment. Outside the arena, deep snowdrifts cover much of an area that is due to be landscaped for the tournament and will host some facilities for fans.

Alexander Fetisov, deputy governor of the Samara region, said the stadium will be ready.

“I’d like to avoid unnecessary dramatization of the situation,” he said. “Everything is being done so that the stadium is commissioned in the time required.”

 

 

Link to comment
Share on other sites

Archived